074-21 - ORDINANCE AMENDING PULASKI COUNTY UNIFIED DEVELOPMENT ORDINANCE Pulaski County Ordinance No. 2021-03

ORDINANCE AMENDING

PULASKI COUNTY UNIFIED DEVELOPMENT ORDINANCE

Pulaski County Ordinance No. 2021-03

WHEREAS, The Pulaski County Board of Commissioners (hereinafter referred to as “the County”) have the power and authority to amend the development fee schedule pursuant to Ind. Code 36-2-4-8; and

WHEREAS, the Advisory Plan Commission (hereinafter referred to as “PCAPC”) did on March 11, 2021 hold a special session meeting to discuss amendments to the Pulaski County Indiana Unified Development Ordinance #2019-08. The PCAPC unanimously moved to amend the UDO under Section 2, Section 3, Section 4 and Section 7 as follows:

PROPOSED:

Section 2

2.3.R.3. Applications for Commercial SES (CSES) special exception hearings. In addition to the application requirements listed in Section 2.3 (R) (1), applications for CSES shall also include the following information:

2.3.R.3.e. “A fire-protection and safety plan for the construction and operation of CSES facility, which includes emergency access to the site. The developer will meet, as required, with township representatives such as trustees, Pulaski County EMS and/or its successor and any and all fire departments providing services and/or mutual aid to address concerns about fire safety and emergency response and coordinate safety planning and potential need of specialized equipment for extinguishing solar-panel/equipment fires. Financial obligations incurred by departments providing coverage in Pulaski County for solar-energy fire-suppression training purposes shall be negotiated as part of development of this plan and any such costs incurred by the developer may be considered during development of Economic Development Agreement.”

2.3.R.3.a.17. map scale (moved up, as #17 was repealed)

2.3.R.3.a.18. Dimensional… (moved up, as #18 was repealed)

2.3.R.3.a.19. dated signature… (moved up, as #19 was repealed)

2.3.R.3.a.20. “Proof of a recorded memorandum of lease for each party contracted with a CSES developer to be recorded at Pulaski County Courthouse within 60 days of special exception approval.”

2.3.R.3.c. The CSES applicant shall… (moved up, as (c) was repealed)

2.3.R.3.d. Any other item reasonable requested by the Board of Zoning Appeals.

2.3.R.5. “After a special exception has been awarded, but before any permits are approved, the CSES developer must provide:

a. proof of correspondence and cooperation with wildlife agencies (i.e. DNR, IDEM, NRCS, etc.) re: endangered species;

b. a Copy of Communications Study(s) providing evidence of compliance with any state and federal agencies regarding communication studies for transmissions such as; GPS, television, microwave, agricultural GPS, military defense systems and radio reception.”

2.3.F.1.a. APC is required to consider a property value guarantee program.

2.3.O.2.c. BZA is required to consider a property value guarantee program.

2.3.P.1.a. BZA is required to consider a property value guarantee program.

***

Section 3

3.5 A-1 D.F. General Agricultural District-Lot Coverage -Lot coverage restrictions are exempt for all CSES panel placement.

3.6 A-2 D.F. Intensive Agriculture District- Lot Coverage -Lot coverage restrictions are exempt for all CSES panel placement.

3.14 L-I D.F. Light Industrial District-Lot Coverage -Lot coverage restrictions are exempt for all CSES panel placement.

3.15 H-I D.F. Heavy Industrial District -Lot coverage restrictions are exempt for all CSES panel placement.

***

Section 4

CSES allowed by special exception approval in L-I & H-I zones

***

Section 7

7.13.B.1. “…visual buffering in the form of evergreen landscaping shall be installed…”

7.14.B.6. “Preference is given to American manufactured components for all CSES but not required. MSDS for all equipment with evidence of the suitability of all proposed equipment with respect to environmental and public safety concerns and comparability to similar American products being provided prior to the issuance of required local permits so as long as all components meet appropriate government standards and requirements.”

7.14.C.1. “All ground-mounted electrical and control equipment for CSES shall be surrounded by a fence no shorter than six (6) feet to prevent unauthorized access. Such fencing shall not include barbed wire but shall be permeable for wildlife passage and within guidelines of state and federal wildlife agencies. Alternative fencing can be used if the site is incorporating agrivoltaics and an agreement is made between neighboring property owner and site developer which shall be recorded at Pulaski County Courthouse.”

7.14.C.3. “The planting of evergreens along the perimeter of the CSES, including along road frontage shall be required and planted on the outside of the perimeter fencing of all occupied residential structures that are non-participating properties that are within half (1/2) of a mile of CSES. Such planting of foliage screening or a properly placed earthen berm, or combination of both shall be of a sufficient height, density and layout to screen the solar site immediately; i.e. planting trees young enough that the objectives of the ordinance cannot be met by the time the project is operational is not acceptable.

While evergreen trees are understood to be the default form of screening; topographical concerns, homeowner preference, developers willingness to accede to requests made by homeowners or County preferences, and the County plan administrator’s preference or approval may lead to alternate forms of visual screening such as deciduous trees. If an individual homeowner would prefer the use of deciduous trees, then the developer would not be held responsible for the presence of the solar site in the homeowner’s view shed during periods of time which said trees have shed their leaves. This does not relieve the developer of the obligation to replace any deciduous or evergreen trees that may lose their ability to grow as the result of disease, damage or other harm for the life of the CSES project.”

7.14.C.3.a. “…process between the developer/owner and the…”

7.14.C.3.a.1. “All property owners subject to the benefits of 7.14.c.3. retain the right to waive the planting requirement and shall have such waiver recorded at Pulaski County Courthouse.”

7.14.C.3.b. REPEALED

7.14.I. Ground cover

7.14.I.1. “Ground area shall be covered, established and maintained with low-growing native perennials, with an emphasis on pollinators and shall be established and maintained in project site, around and under solar panels and buffer areas for the life of the CSES project. Consultation with (a) biologist(s) and/or other relevant experts approved by the administrator shall be part of the development process to ensure that plantings and tracker/panel layout on solar-energy site accomplish the following:

a.) minimize “lake effect” impact on birds flying overhead to the greatest extent practicable as judged by a qualified professional;

b.) encourage nesting grassland birds;

c.) limit the number of times the property is mowed during the year to the fewest number of times reasonable as judged by a qualified professional;

d.) induce frequenting of the sites by bees for pollination;

e.) in conjunction with required screening measures, ensure the properties’ appearance relative to nearby environs creates as little contrast as possible.

f.) control chemical and pesticide management

g.) maintained to be free of invasive or noxious species, such as listed by Indiana Department of Natural Resources (DNR)

This shall not be limited to discourage dual use of any solar-energy sites, when possible, for the purpose of allowing livestock grazing, apiaries, or other compatible, agricultural uses. Additionally, plantings within any 75’ setback to a ditch shall comply with USDA Farm Service Agency guidelines for appropriate plantings for filter strips.”

7.15.A.1. “Noise from a CSES shall not exceed 50 dB measured from the nearest property line. This restriction is not expected to be met during project construction or short-term periods of repair or maintenance including grounds keeping (such as mowing), except between 7:00 p.m. and 7:00 a.m. Third-party–study evidence of the project’s ability to comply with this condition shall be provided prior to issuance of improvement-location and building permits. This limit may be waived by any adjoining property owner in writing and recorded at Pulaski County Courthouse. All other noise and vibration levels shall be in compliance with all state and federal regulations. All CSES shall be designed, and reflection angles oriented, to avoid concentrated and prolonged glare into abutting structures and roadways.”

7.14.H.1. “…generated from supplies, equipment, energy storage, parts…”

7.15.E.1. “All SES shall be installed so as not to cause significant wire or wireless communication signal disturbance for such transmissions to include but not limited to GPS, television, microwave, agricultural GPS, military defense systems and radio reception.”

7.16.C. “Operation of an SES shall minimize interference with public servicing utility microwave transmission to include but not limited to GPS, television, microwave, agricultural GPS, military defense systems and radio receptions. If necessary, the applicant, owner and/or operator shall mitigate interference with electromagnetic communications, such as radio, telephone, microwaves, or television signals caused by any SES….”

7.17 Table 7.3 Minimum Setbacks

From any CSES component to an internal ditch 75’

From any CSES component to a non-participating/

     non-included property line or any right of way. 150’

Inverter or converter to a communications tower. 1.1 times the total 

height of the tower

7.18.A.2.a. “…;economic development payments to be made to the County…”

7.18.A.2.b. “The DA must prescribe…before any building permit is issued. The DA shall show evidence of compliance with storm drainage, erosion, and sediment control regulations (Rule 5).”

7.18.A.2.c. “…a CSES developer shall to the greatest….assurance to the County pertaining to the developer/owner’s ability to repair…”

7.18.A.7. “proof of correspondence and cooperation with wildlife agencies to include but not limited to DNR, IDEM, NRCS.”

7.18.A.8. “Copy of Communications Study(s) providing evidence of compliance with any state and federal agencies with jurisdiction requiring such studies.”

7.19.A.4. “The developer/owner shall adhere to…”

7.19.A.5. “The developer/owner shall adhere to…”

7.20.A.4. Commercial SES Post-Construction Requirements – Maintenance Records

“Annually, the CSES developer shall provide to the Building Department proof of required and periodic maintenance with proof of safe maintenance. If Building Department doesn’t received required verification within 30 days of their requested notice, the Building Department may hire a qualified external inspector to perform CSES system inspections.”

WHEREAS, the County being duly advised now approves said recommendations by the PCAPC; and

THEREFORE, BE IT ORDAINED THAT:

The Pulaski County Unified Development Ordinance is hereby amended under Section 2, Section 3, Section 4, and Section 7 to include the following language:

PROPOSED:

Section 2

2.3.R.3. Applications for Commercial SES (CSES) special exception hearings. In addition to the application requirements listed in Section 2.3 (R) (1), applications for CSES shall also include the following information:

2.3.R.3.e. “A fire-protection and safety plan for the construction and operation of CSES facility, which includes emergency access to the site. The developer will meet, as required, with township representatives such as trustees, Pulaski County EMS and/or its successor and any and all fire departments providing services and/or mutual aid to address concerns about fire safety and emergency response and coordinate safety planning and potential need of specialized equipment for extinguishing solar-panel/equipment fires. Financial obligations incurred by departments providing coverage in Pulaski County for solar-energy fire-suppression training purposes shall be negotiated as part of development of this plan and any such costs incurred by the developer may be considered during development of Economic Development Agreement.”

2.3.R.3.a.17. map scale (moved up, as #17 was repealed)

2.3.R.3.a.18. Dimensional… (moved up, as #18 was repealed)

2.3.R.3.a.19. dated signature… (moved up, as #19 was repealed)

2.3.R.3.a.20. “Proof of a recorded memorandum of lease for each party contracted with a CSES developer to be recorded at Pulaski County Courthouse within 60 days of special exception approval.”

2.3.R.3.c. The CSES applicant shall… (moved up, as (c) was repealed)

2.3.R.3.d. “Any other item reasonable requested by the Board of Zoning Appeals.”

2.3.R.5. “After a special exception has been awarded, but before any permits are approved, the CSES developer must provide:

a. proof of correspondence and cooperation with wildlife agencies (i.e. DNR, IDEM, NRCS, etc.) re: endangered species;

b. a Copy of Communications Study(s) providing evidence of compliance with any state and federal agencies regarding communication studies for transmissions such as; GPS, television, microwave, agricultural GPS, military defense systems and radio reception.”

2.3.F.1.a. APC is required to consider a property value guarantee program.

2.3.O.2.c. BZA is required to consider a property value guarantee program for use variances.

2.3.P.1.a. BZA is required to consider a property value guarantee program.

***

Section 3

3.5 A-1 D.F. General Agricultural District-Lot Coverage -Lot coverage restrictions are exempt for all CSES panel placement.

3.6 A-2 D.F. Intensive Agriculture District- Lot Coverage -Lot coverage restrictions are exempt for all CSES panel placement.

3.14 L-I D.F. Light Industrial District-Lot Coverage -Lot coverage restrictions are exempt for all CSES panel placement.

3.15 H-I D.F. Heavy Industrial District -Lot coverage restrictions are exempt for all CSES panel placement.

***

Section 4

CSES allowed by special exception approval in L-I & H-I zones

***

Section 7

7.13.B.1. “…visual buffering in the form of evergreen landscaping shall be installed…”

7.14.B.6. “Preference is given to American manufactured components for all CSES but not required. MSDS for all equipment with evidence of the suitability of all proposed equipment with respect to environmental and public safety concerns and comparability to similar American products being provided prior to the issuance of required local permits so as long as all components meet appropriate government standards and requirements.”

7.14.C.1. “All ground-mounted electrical and control equipment for CSES shall be surrounded by a fence no shorter than six (6) feet to prevent unauthorized access. Such fencing shall not include barbed wire but shall be permeable for wildlife passage and within guidelines of state and federal wildlife agencies. Alternative fencing can be used if the site is incorporating agrivoltaics and an agreement is made between neighboring property owner and site developer which shall be recorded at Pulaski County Courthouse.”

7.14.C.3. “The planting of evergreens along the perimeter of the CSES, including along road frontage shall be required and planted on the outside of the perimeter fencing of all occupied residential structures that are non-participating properties that are within half (1/2) of a mile of CSES. Such planting of foliage screening or a properly placed earthen berm, or combination of both shall be of a sufficient height, density and layout to screen the solar site immediately; i.e. planting trees young enough that the objectives of the ordinance cannot be met by the time the project is operational is not acceptable.

While evergreen trees are understood to be the default form of screening; topographical concerns, homeowner preference, developers willingness to accede to requests made by homeowners or County preferences, and the County plan administrator’s preference or approval may lead to alternate forms of visual screening such as deciduous trees. If an individual homeowner would prefer the use of deciduous trees, then the developer would not be held responsible for the presence of the solar site in the homeowner’s view shed during periods of time which said trees have shed their leaves. This does not relieve the developer of the obligation to replace any deciduous or evergreen trees that may lose their ability to grow as the result of disease, damage or other harm for the life of the CSES project.”

7.14.C.3.a. “…process between the developer/owner and the…”

7.14.C.3.a.1. “All property owners subject to the benefits of 7.14.c.3. retain the right to waive the planting requirement and shall have such waiver recorded at Pulaski County Courthouse.”

7.14.C.3.b. REPEALED

7.14.I. Ground cover

7.14.I.1. “Ground area shall be covered, established and maintained with low-growing native perennials, with an emphasis on pollinators and shall be established and maintained in project site, around and under solar panels and buffer areas for the life of the CSES project. Consultation with (a) biologist(s) and/or other relevant experts approved by the administrator shall be part of the development process to ensure that plantings and tracker/panel layout on solar-energy site accomplish the following:

a.) minimize “lake effect” impact on birds flying overhead to the greatest extent practicable as judged by a qualified professional;

b.) encourage nesting grassland birds;

c.) limit the number of times the property is mowed during the year to the fewest number of times reasonable as judged by a qualified professional;

d.) induce frequenting of the sites by bees for pollination;

e.) in conjunction with required screening measures, ensure the properties’ appearance relative to nearby environs creates as little contrast as possible.

f.) control chemical and pesticide management

g.) maintained to be free of invasive or noxious species, such as listed by Indiana Department of Natural Resources (DNR)

This shall not be limited to discourage dual use of any solar-energy sites, when possible, for the purpose of allowing livestock grazing, apiaries, or other compatible, agricultural uses. Additionally, plantings within any 75’ setback to a ditch shall comply with USDA Farm Service Agency guidelines for appropriate plantings for filter strips.”

7.15.A.1. “Noise from a CSES shall not exceed 50 dB measured from the nearest property line. This restriction is not expected to be met during project construction or short-term periods of repair or maintenance including grounds keeping (such as mowing), except between 7:00 p.m. and 7:00 a.m. Third-party–study evidence of the project’s ability to comply with this condition shall be provided prior to issuance of improvement-location and building permits. This limit may be waived by any adjoining property owner in writing and recorded at Pulaski County Courthouse. All other noise and vibration levels shall be in compliance with all state and federal regulations. All CSES shall be designed, and reflection angles oriented, to avoid concentrated and prolonged glare into abutting structures and roadways.”

7.14.H.1. “…generated from supplies, equipment, energy storage, parts…”

7.15.E.1. “All SES shall be installed so as not to cause significant wire or wireless communication signal disturbance for such transmissions to include but not limited to GPS, television, microwave, agricultural GPS, military defense systems and radio reception.”

7.16.C. “Operation of an SES shall minimize interference with public servicing utility microwave transmission to include but not limited to GPS, television, microwave, agricultural GPS, military defense systems and radio receptions. If necessary, the applicant, owner and/or operator shall mitigate interference with electromagnetic communications, such as radio, telephone, microwaves, or television signals caused by any SES….”

7.17 Table 7.3 Minimum Setbacks

From any CSES component to an internal ditch 75’

From any CSES component to a non-participating/

     non-included property line or any right of way. 150’

Inverter or converter to a communications tower. 1.1 times the total 

height of the tower

7.18.A.2.a. “…;economic development payments to be made to the County…”

7.18.A.2.b. “The DA must prescribe…before any building permit is issued. The DA shall show evidence of compliance with storm drainage, erosion, and sediment control regulations (Rule 5).”

7.18.A.2.c. “…a CSES developer shall to the greatest….assurance to the County pertaining to the developer/owner’s ability to repair…”

7.18.A.7. “proof of correspondence and cooperation with wildlife agencies to include but not limited to DNR, IDEM, NRCS.”

7.18.A.8. “Copy of Communications Study(s) providing evidence of compliance with any state and federal agencies with jurisdiction requiring such studies.”

7.19.A.4. “The developer/owner shall adhere to…”

7.19.A.5. “The developer/owner shall adhere to…”

7.20.A.4. Commercial SES Post-Construction Requirements – Maintenance Records

“Annually, the CSES developer shall provide to the Building Department proof of required and periodic maintenance with proof of safe maintenance. If Building Department doesn’t received required verification within 30 days of their requested notice, the Building Department may hire a qualified external inspector to perform CSES system inspections.”

Pursuant to Ind. Code 36-2-4-8 (e) this ordinance will be published one time within thirty (30) days from April 5, 2021 in accordance with Ind. Code 5-3-1. Implementation of the fee increase shall begin ninety (90) days after the date of publication.

Passed and adopted by the Board of County Commissioners of Pulaski County, Indiana, this 5th day of April, 2021 and effective ninety (90) days after the first publication, but no later than June 30, 2021.

All other aspects and language of the Development Fee Schedule adopted January 1, 2020 shall remain in full force and effect.

Charles R. “Chuck” Mellon, President; Maurice E. Loehmer, Vice-President; John M. “Mike” McClure, Member

Attest: Laura Wheeler, Auditor